Top Story – March 26, 2025

-by April MacDonald

Les Hodgkins with the IDA let us know that there were a number of people asking questions about the equipment down at the Inverness Beach below the boardwalk, wondering who was doing work and what exactly was being done.

Hodgkins suggested speaking with Melanie Beaton, deputy CAO for the Municipality of the County of Inverness to get the full story.

There is an issue with the wastewater overflow pipe from the service treatment centre plant under the boardwalk; we caught up with Beaton to learn more.

“Our Chief Communications Officer will be issuing a press release when we have a more concrete timeline,” said Beaton.

“We [the County] plan to replace a section of pipe, it’s actually from the last manhole on the high side of the boardwalk and it goes to the beach,” she explained.

Beaton said that as it is a highly eco-sensitive area; a great many permits are needed to do the work.

“We also have to avoid bird nesting season which runs from April 15th to the end of August. We are hoping to have onshore mobilized prior to bird nesting,” said Beaton.

Zutphens Contracting has been awarded the tender.

“We still have outstanding permits waiting. The machinery has been put down at the beach by Zutphens Contracting ahead of time as weight restrictions are now in effect on the roads, that’s why the machines and equipment are down on the site now,” explained the deputy CAO.

Beaton wanted to highlight that this is already an existing pipe that they are replacing; it’s not a new pipe being installed.

They have secured permits already from the Department of Fisheries and Oceans, Transport Canada, Nova Scotia Department of Environment and Climate Change, and the Nova Scotia Department of Natural Resources and Renewables.

“If we can’t get the final permits before bird nesting season, then the work will have to be done in the fall, as we don’t want to impact beach goers and golfers,” said Beaton.

She closed by explaining that the county wanted to issue a public communication but it was challenging as they don’t have a concrete schedule for the work to commence, “once that is known and when the public will be impacted there will be a formal release issued.”